7 November 2026 · Bearsource
Every launch plan starts the same way: "Production takes six weeks, so we launch in June." Then June becomes August, and nobody can point to the week it went wrong — because it didn't go wrong in one week. A production timeline is not one block of time. It's a chain of separate waits: samples, tooling, materials, a slot in the factory's queue, inspection, a ship. Timelines slip at the links of that chain, not in the middle of them. Here are the six places yours will slip, what each one really costs, and how operators plan around them.
When a factory quotes "45 days production," they are quoting one thing: the run itself, from the day materials are on their floor to the day cartons are sealed. Everything before and after that run is real time that somebody has to own:
Add it honestly and a first order commonly lands five to seven months after you said "go." The factory didn't lie to you. You just planned with one number out of six.
Each sampling round costs more time than anyone budgets. The factory needs 5–10 days to make the sample. Courier to you: 3–5 days. Your review, internal comments, and a consolidated reply: rarely less than a week. One round is two to three weeks of calendar, and three rounds is a normal first product. Five is not rare.
What turns three rounds into five is vague feedback. "Make it feel more premium" is not an instruction a factory can execute — it buys you one more full round while they guess. What kills rounds is precision: measurements against the spec, marked-up photos, a short video showing the problem, and one consolidated comment list per round instead of a drip of emails. Then lock it: a signed-off golden sample that production is later measured against. We covered why that sample discipline matters in Good sample, bad product — the short version is that the sample you approve casually becomes the standard you argue about later.
An injection mold typically takes 25–45 days from drawing approval to first trial shots (the T1 samples). Almost no mold is right at T1. What matters is what happens next: changes made before steel is hardened are cheap; changes after cutting — welding up a cavity, re-machining a core — add one to three weeks each, plus a new trial round. Two revision loops on a first mold is normal. Four means the design wasn't finished when tooling started.
The rule is boring and absolute: freeze the design before you cut steel, and treat every change after that as a schedule decision, not a design decision. Who owns the finished mold is a separate question with its own paperwork — see Who owns your mold? — but even a perfectly owned mold can't give you back the weeks a late change burns.
Here is the quietest slip of the six: production cannot start until the longest-lead component is physically in the factory. Standard fabrics, zippers, and hardware run two to four weeks. A custom-dyed fabric is three to five. Motors, PCBs, and specific chips can run six to sixteen weeks when supply is tight. Printed packaging — the item everyone forgets — is two to three weeks on its own.
Notice what the factory's quote assumes: "30 days production" starts when materials arrive. If the motor lands in week seven, your 30 days start in week seven. Ask for the material list with an ETA per item, not a production date. The longest ETA on that list is your real start line, and it's the one number most buyers never ask for.
Factories don't run at one speed all year, and they don't queue orders in the order purchase orders arrive. Your slot in line is set by two things: deposit paid and materials confirmed. Until both are true, you are not in the queue — you are in the inbox.
Chinese New Year is the extreme case. Factories close for two to four weeks, workers return staggered over the following weeks, and the effective loss is four to six weeks of capacity. Every buyer in the world knows this, so the eight weeks before the holiday become a rush that pushes lead times out further — an order confirmed in December can find itself behind a wall of earlier confirmations. Golden Week in early October takes another week. None of this is a surprise event. All of it is on the calendar years in advance, and it still catches launch plans every single year.
A defect pattern discovered at final inspection is the most expensive discovery in manufacturing, because the only fixes are rework or re-run — two to four weeks if you're lucky, the whole schedule if you're not. And final inspection is where most buyers discover defects, because it's the only inspection they arranged.
Finding problems late is a choice. Checks at material arrival, a first-article check when the line starts, and one mid-production check catch the same defects when they cost hours instead of weeks. A final AQL inspection is still worth doing — but understand what it is: a verdict on finished goods, not a control on the process. Our factory audit checklist walks through where these checkpoints belong. The principle is simple: the earlier a defect is found, the cheaper it is — in money, and even more in weeks.
Finished goods are not shipped goods. In peak season — roughly August through October for US-bound cargo — vessel space tightens, bookings get rolled to the next sailing, and a one-to-two-week slip at the dock is common. Normal practice is to book two to three weeks before the goods are ready; a factory that finishes "early" into a full ship has gained you nothing, and a late finish can lose a booked slot entirely.
Smaller frictions add up here too: EXW orders where nobody arranged the pickup, cartons that miss the warehouse cut-off, a customs exam that adds days nobody budgeted. We mapped the current state of delays in China shipment delays. The planning point stands on its own: your timeline ends when the goods are in your warehouse, not when they leave the factory floor — count backwards from the warehouse date.
Most of what you've just read is not sourcing. Sourcing — finding and vetting the factory — is the first week of the job. The other twenty weeks are this: running the milestone list, sitting inside the sampling loop until the comments are precise, confirming materials are physically in the building, inspecting during production instead of after it, and booking freight against the real readiness date. That's production management, and it's the work BearSource is built around — from the first idea to the shipment arriving. The full path is in how it works, and our fees are published on the pricing page.
My factory says 30 days. What should I actually plan?
Plan on the chain, not the run. For a repeat product with materials available domestically, 10–14 weeks from deposit to vessel is realistic. For a first order with tooling, five to seven months to your warehouse is the honest number. If your launch can't survive that, the fix is starting earlier or cutting scope — not pressuring the one number that was never the problem.
What's the single biggest cause of lateness?
In our experience it's the combination nobody owns: slow, vague sample approval on the buyer's side, plus a long-lead material nobody tracked. Factories get blamed for the sum of both. The factories cause their share too — queue-jumping for bigger customers is real — which is why the milestone list with evidence matters.
Can I pay extra to go faster?
Sometimes, in specific places: faster sample couriers, overtime on a rework, ordering materials in parallel instead of in sequence. Where it usually fails is at the end — air-freighting a full order to rescue a date typically costs more than the launch margin it saves. Speed money works best spent early, on the links of the chain, not on the last one.
Working against a launch date? Send us the timeline your factory gave you. We'll mark the places it will slip — while there's still time to do something about them.